| ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
| 1 | Detailed Development plan for fund raising | 788 days | Jul 1 | Jul 6 | Alen Brown,Development Dir. | 53% |
| 2 | Create Marketing Presentation | 163 days | Jul 1 | Feb 11 | Alen Brown | 100% |
| 3 | Initial DVD Presentation | 37 days | Jul 13 | Sep 1 | Alen Brown | 100% |
| 4 | Initial Power Point Presentation | 40 days | Sep 1 | Oct 26 | Alen Brown | 100% |
| 5 | Revise Presentation Roles | 15 days | Dec 21 | Jan 7 | Alen Brown,Development Dir. | 100% |
| 6 | Complete Promotional DVD | 30 days | Jan 3 | Feb 11 | Alen Brown | 100% |
| 7 | Complete Power Point | 10 days | Jan 3 | Jan 14 | Alen Brown | 100% |
| 8 | Research & Create Literature | 45 days | Jul 1 | Sep 1 | Alen Brown | 100% |
| 9 | Create Publicity Campaign Plan | 292 days | Jul 1 | Aug 11 | Alen Brown | 99% |
| 10 | Devise Literature Distribution Scheme | 10 days | Jan 18 | Jan 31 | Alen Brown,Development Dir. | 100% |
| 11 | Send out first solicitation; ED Friends/Family | 30 days | Jun 20 | Jul 29 | Alen Brown | 100% |
| 12 | Media Contact | 292 days | Jul 1 | Aug 11 | Alen Brown | 99% |
| 13 | Paulding Media | 30 days | Jul 1 | Dec 31 | Alen Brown,Development Dir. | 100% |
| 14 | Atlanta Media | 118 days | Mar 1 | Aug 11 | Alen Brown,Development Dir. | 99% |
| 15 | Initial Articles | 10 days | Mar 1 | Mar 14 | Alen Brown | 100% |
| 16 | Followup Articles | 30 days | Jul 1 | Aug 11 | Alen Brown,Development Dir. | 100% |
| 17 | Foundations Plan | 214 days | Oct 1 | Jul 26 | Alen Brown,Development Dir. | 99% |
| 18 | Cassin Foundation Grant (150K) | 22 days | Nov 1 | Nov 30 | Alen Brown,Deborah Betsill | 100% |
| 19 | | 66 days | Oct 1 | Feb 18 | Deborah Betsill,Allene Edwards | 100% |
| 20 | Research each potential and refine list | 30 days | Dec 23 | Feb 1 | Alen Brown,Development Dir. | 100% |
| 21 | Create priority List | 10 days | Feb 2 | Feb 15 | Alen Brown,Development Dir. | 100% |
| 22 | Make Applications and Track | 115 days | Feb 16 | Jul 26 | Development Dir.,Alen Brown | 99% |
| 23 | Initial 20 Proposals | 60 days | Feb 16 | May 10 | Deborah Betsill,Allene Edwards | 100% |
| 24 | Evaluation of results | 15 days | May 11 | May 31 | Alen Brown,Development Dir. | 100% |
| 25 | Revise Procedure | 10 days | Jun 1 | Jun 14 | Alen Brown,Development Dir. | 100% |
| 26 | Create ongoing grant submission process | 30 days | Jun 15 | Jul 26 | Alen Brown,Development Dir. | 100% |
| 27 | Corporations Plan | 491 days | Jul 1 | May 18 | Alen Brown,Development Dir. | 14% |
| 28 | Define Target Corporations | 45 days | Jul 1 | Sep 1 | Alen Brown,Development Dir. | 100% |
| 29 | Create Priority List | 10 days | Sep 2 | Sep 15 | Alen Brown,Development Dir. | 100% |
| 30 | Find Champions within Each Company | 336 days | Sep 16 | Dec 29 | Alen Brown,Development Dir.,Board Members | 3% |
| 31 | Make Applications and Track | 100 days | Jan 1 | May 18 | Alen Brown,Development Dir. | 0% |
| 32 | Individuals Plan | 134 days | Feb 1 | Aug 5 | Alen Brown,Development Dir. | 99% |
| 33 | Devise Plan | 20 days | Feb 1 | Feb 28 | Alen Brown,Development Dir.,Board Members | 100% |
| 34 | Research and Find Potentials | 65 days | Mar 2 | May 31 | Alen Brown,Development Dir.,Board Members | 100% |
| 35 | Create Target List | 30 days | Jun 1 | Jul 12 | Alen Brown,Development Dir.,Board Members | 100% |
| 36 | Make Presentations and Track | 35 days | Jun 20 | Aug 5 | Alen Brown,Development Dir.,Board Members | 99% |
| 37 | Paulding Individuals Mailing | 5 days | Jun 20 | Jun 24 | Alen Brown,Development Dir.,Board Members | 100% |
| 38 | Exec Dir Friends | 5 days | Jun 20 | Jun 24 | Alen Brown | 100% |
| 39 | Board Member Friends | 25 days | Jul 4 | Aug 5 | Alen Brown,Development Dir.,Board Members | 100% |
| 40 | Sponsor Groups Plan | 596 days | Jan 1 | Apr 13 | Alen Brown,Development Dir. | 54% |
| 41 | Devise Plan | 20 days | Jan 1 | Jan 27 | Alen Brown,Deborah Betsill | 100% |
| 42 | Research and Find Potentials | 20 days | Jan 28 | Feb 24 | Alen Brown,Deborah Betsill | 100% |
| 43 | Create Target List | 10 days | Feb 25 | Mar 10 | Alen Brown,Development Dir. | 100% |
| 44 | Obtain Non-Profit mailing status from USPO | 20 days | Jun 27 | Jul 22 | Alen Brown,Development Dir. | 100% |
| 45 | Make Presentations and Track | 554 days | Mar 1 | Apr 13 | Alen Brown,Development Dir. | 53% |
| 46 | Episcopal | 546 days | Mar 11 | Apr 13 | Alen Brown,Development Dir. | 52% |
| 47 | St. Teresa's | 250 days | Jul 25 | Jul 7 | Alen Brown,Deborah Betsill | 80% |
| 48 | St. David's | 416 days | Mar 11 | Jan 5 | Alen Brown,Deborah Betsill | 70% |
| 49 | St. Martin's | 60 days | Apr 1 | Sep 12 | Alen Brown,Development Dir. | 100% |
| 50 | Marietta Convocation | 337.5 days | Mar 11 | Oct 13 | Alen Brown,Deborah Betsill | 75% |
| 51 | NW Georgia Convocation | 402.5 days | Mar 11 | Jan 12 | Alen Brown,Development Dir. | 40% |
| 52 | Mid-Atlanta Convocation | 392 days | Mar 11 | Jan 12 | Alen Brown,Deborah Betsill | 60% |
| 53 | East Metro Atlanta Convocation | 388 days | Mar 11 | Jan 5 | Alen Brown,Development Dir. | 25% |
| 54 | St. Luke's | 383 days | Jul 1 | Jan 5 | Alen Brown,Development Dir. | 25% |
| 55 | Sewanee Alumni | 448 days | Jul 1 | Apr 6 | Alen Brown,Development Dir. | 75% |
| 56 | ECW | 450 days | Jul 25 | Apr 13 | Alen Brown,Development Dir. | 40% |
| 57 | Cursillo | 450 days | Jul 25 | Apr 13 | Alen Brown,Deborah Betsill | 60% |
| 58 | BSA | 450 days | Jul 25 | Apr 13 | Alen Brown,Development Dir. | 25% |
| 59 | Paulding Business | 434 days | Jun 1 | Mar 9 | Alen Brown,Development Dir. | 60% |
| 60 | Paulding Faith | 404 days | Mar 1 | Jan 5 | Alen Brown,Development Dir. | 50% |
| 61 | Exec Dir Friends & Family | 66.6 days | Jun 20 | Sep 29 | Alen Brown,Development Dir. | 100% |
| 62 | Events Plan | 88 days | Jun 1 | Sep 30 | Development Dir. | 100% |
| 63 | Create Priority List of Events | 88 days | Jun 1 | Sep 30 | Alen Brown,Development Dir. | 100% |
| 64 | Paulding | 20 days | Jun 1 | Jun 28 | Alen Brown,Development Dir. | 100% |
| 65 | Diocese | 45 days | Aug 1 | Sep 30 | Alen Brown,Development Dir. | 100% |
| 66 | Atlanta Metro | 45 days | Aug 1 | Sep 30 | Alen Brown,Development Dir. | 100% |
| 67 | Plan Charity Golf Tourney | 24 days | Jun 1 | Jul 4 | Kevin Bagwell,Alen Brown,Development Dir. | 100% |
| 68 | Student Fees Plan | 113 days | Jun 27 | Nov 30 | Alen Brown,Development Dir. | 4% |
| 69 | Research Other Schools | 25 days | Jun 27 | Jul 29 | Joyce Nicholson | 0% |
| 70 | Focus Group Input | 1 day | Sep 30 | Sep 30 | Alen Brown | 100% |
| 71 | Decide on Monthly Fee | 1 day | Nov 30 | Nov 30 | Alen Brown | 0% |
| 72 | Funding from Gov't for Kids on Free/Reduced Lunch Program | 696 days | Oct 1 | May 31 | Joyce Nicholson | 22% |
| 73 | Research Possibilities | 30 days | Oct 1 | May 2 | Joyce Nicholson | 100% |
| 74 | Instigate request for funding and Track | 109 days | Jan 1 | May 31 | Joyce Nicholson | 0% |
| 75 | Attend Nativity Development Conference | 5 days | Oct 10 | Oct 14 | Alen Brown,Development Dir. | 100% |
| 76 | Development Training | 5 days | Jan 9 | Jan 13 | Alen Brown,Development Dir. | 0% |
| 77 | Raise $800,000 by August 2007 | 788 days | Jul 1 | Jul 6 | Alen Brown,Development Dir. | 30% |
| 78 | Develop Board of Directors | 773 days | Jul 15 | Jun 29 | Alen Brown,Development Dir. | 79% |
| 79 | Define Roles of Board members | 66 days | Oct 5 | Jan 3 | Board Members | 100% |
| 80 | Defines Characteristics of Needed Board Members | 88 days | Oct 1 | Jan 31 | Board Members | 100% |
| 81 | Board Meeting | 527 days | Jul 15 | Jul 20 | Board Members | 100% |
| 82 | Board Meeting 1 | 1 day | Jul 15 | Jul 15 | | 100% |
| 83 | Board Meeting 2 | 1 day | Aug 19 | Aug 19 | | 100% |
| 84 | Board Meeting 3 | 1 day | Sep 16 | Sep 16 | | 100% |
| 85 | Board Meeting 4 | 1 day | Oct 21 | Oct 21 | | 100% |
| 86 | Board Meeting 5 | 1 day | Nov 18 | Nov 18 | | 100% |
| 87 | Board Meeting 6 | 1 day | Dec 16 | Dec 16 | | 100% |
| 88 | Board Meeting 7 | 1 day | Jan 20 | Jan 20 | | 100% |
| 89 | Board Meeting 8 | 1 day | Feb 17 | Feb 17 | | 100% |
| 90 | Board Meeting 9 | 1 day | Mar 17 | Mar 17 | | 100% |
| 91 | Board Meeting 10 | 1 day | Apr 21 | Apr 21 | | 100% |
| 92 | Board Meeting 11 | 1 day | May 19 | May 19 | | 100% |
| 93 | Board Meeting 12 | 1 day | Jun 16 | Jun 16 | | 100% |
| 94 | Board Meeting 13 | 1 day | Jul 21 | Jul 21 | | 100% |
| 95 | Board Meeting 14 | 1 day | Aug 18 | Aug 18 | | 100% |
| 96 | Board Meeting 15 | 1 day | Sep 15 | Sep 15 | | 100% |
| 97 | Board Meeting 16 | 1 day | Oct 20 | Oct 20 | | 100% |
| 98 | Board Meeting 17 | 1 day | Nov 17 | Nov 17 | | 100% |
| 99 | Board Meeting 18 | 1 day | Dec 15 | Dec 15 | | 100% |
| 100 | Board Meeting 19 | 1 day | Jan 19 | Jan 19 | | 100% |
| 101 | Board Meeting 20 | 1 day | Feb 16 | Feb 16 | | 100% |
| 102 | Board Meeting 21 | 1 day | Mar 16 | Mar 16 | | 100% |
| 103 | Board Meeting 22 | 1 day | Apr 20 | Apr 20 | | 100% |
| 104 | Board Meeting 23 | 1 day | May 18 | May 18 | | 100% |
| 105 | Board Meeting 24 | 1 day | Jun 15 | Jun 15 | | 100% |
| 106 | Board Meeting 25 | 1 day | Jul 20 | Jul 20 | | 100% |
| 107 | Define Committees | 161 days | Jul 1 | Feb 10 | Board Members | 100% |
| 108 | Finance/Fundraising | 30 days | Jul 1 | Aug 11 | Board Members | 100% |
| 109 | Curriculum | 30 days | Sep 5 | Oct 14 | Board Members | 100% |
| 110 | Admissions | 30 days | Jan 2 | Feb 10 | Board Members | 100% |
| 111 | Facilities | 30 days | Sep 5 | Oct 14 | Board Members | 100% |
| 112 | Establish Board of 9 members | 30 days | May 9 | Jun 17 | Board Members | 100% |
| 113 | Meet with all potential candidates to determine sincerity | 30 days | May 9 | Jun 17 | Board Members | 100% |
| 114 | Nominate and elect new members | 1 day | May 30 | May 30 | Board Members | 100% |
| 115 | Grow Board to 15 members | 521 days | Jul 1 | Jun 29 | Board Members | 65% |
| 116 | High level of quality education | 645.01 days | Jan 3 | Jun 25 | Development Dir. | 60% |
| 117 | Research and Identify appropriate curriculum | 387 days | Sep 1 | Feb 23 | Principal,Gail Snipes | 74% |
| 118 | Research and Identify appropriate core curriculum | 237 days | Sep 1 | Jul 28 | Joyce Nicholson,Development Dir.,Gail Snipes | 90% |
| 119 | Acquire core curriculum | 45 days | Dec 25 | Feb 23 | Gail Snipes | 0% |
| 120 | Research and Identify appropriate religious curriculum | 199 days | Nov 1 | Aug 4 | Joyce Nicholson,Development Dir. | 80% |
| 121 | Acquire religious curriculum | 20 days | Jan 1 | Jan 26 | Gail Snipes,Alen Brown | 0% |
| 122 | Proving children are doing well on a given curriculum | 248 days | Feb 1 | Jan 12 | Development Dir. | 32% |
| 123 | Research baseline testing instrument | 30 days | Feb 1 | Mar 14 | Development Dir. | 90% |
| 124 | Decide on baseline test | 183 days | Mar 15 | Nov 24 | Gail Snipes | 25% |
| 125 | Acquire baseline test | 15 days | Dec 25 | Jan 12 | Gail Snipes | 0% |
| 126 | 1 Master Teacher for every Department | 22.3 days | Oct 3 | Nov 2 | Gail Snipes | 70% |
| 127 | Policy | 5 days | Oct 3 | Oct 12 | Gail Snipes | 70% |
| 128 | Define "Master Teacher" and certification reqs | 15 days | Oct 12 | Nov 2 | Gail Snipes | 70% |
| 129 | Extended school day, extended school year | 405.01 days | Dec 5 | Jun 25 | Principal,Gail Snipes | 61% |
| 130 | Define 'extended' in day | 405.01 days | Dec 5 | Jun 25 | Principal,Gail Snipes | 76% |
| 131 | Actual Definition of day | 405.01 days | Dec 5 | Jun 25 | Principal,Gail Snipes | 76% |
| 132 | Core Subjects | 24.75 days | Dec 5 | Jan 6 | Principal,Gail Snipes | 90% |
| 133 | Extracurricular activities | 174.85 days | Dec 5 | Jun 22 | Principal,Gail Snipes | 75% |
| 134 | Study Hall | 162.38 days | Dec 5 | Jun 25 | Principal,Gail Snipes | 75% |
| 135 | Define 'extended' in year | 268 days | Feb 1 | Feb 9 | Principal,Gail Snipes | 54% |
| 136 | Actual Definition of year | 37.78 days | Feb 1 | Jan 3 | Gail Snipes,Alen Brown | 80% |
| 137 | Decide if Summer 07 Program is possible | 225 days | Apr 3 | Feb 9 | Gail Snipes,Alen Brown | 50% |
| 138 | Define resource plan associated with above | 230 days | May 1 | Mar 16 | Gail Snipes,Alen Brown | 50% |
| 139 | Providing opportunity to engage in extracurricular activities | 30 days | May 1 | Jun 9 | Gail Snipes,Alen Brown | 30% |
| 140 | Nurturing, safe environment | 566 days | Jan 3 | Mar 5 | Joyce Nicholson | 54% |
| 141 | Define safe environment..security measures, etc. | 284 days | Feb 1 | Mar 5 | Joyce Nicholson | 51% |
| 142 | Define safe environment..security measures, etc. | 10 days | Feb 1 | Feb 14 | Joyce Nicholson | 70% |
| 143 | Compare/contrast public & private requirements | 10 days | Feb 15 | Feb 28 | Joyce Nicholson | 70% |
| 144 | Review w/Legal | 3 days | Mar 1 | Mar 3 | Alen Brown | 100% |
| 145 | Define health support process in lieu of staff nurse/clinic | 8 days | Mar 1 | Mar 10 | Joyce Nicholson,Alen Brown | 10% |
| 146 | Define methods for counseling | 243 days | Mar 22 | Feb 23 | Faith Turner | 50% |
| 147 | Behavioral rules in place to support a safe environment | 15 days | May 3 | Mar 5 | Alen Brown,Gail Snipes | 60% |
| 148 | Low student to teacher ratio | 20 days | Jan 3 | Jan 28 | Alen Brown,Principal,Gail Snipes | 100% |
| 149 | 15 to 1 ratio | 20 days | Jan 3 | Jan 28 | Alen Brown,Principal,Gail Snipes | 100% |
| 150 | Policy targeted, allow for flexibility | 20 days | Jan 3 | Jan 28 | Alen Brown | 100% |
| 151 | Research success and failues of Charter Schools | 20.08 days | Mar 1 | Mar 29 | Alen Brown,Principal,Gail Snipes | 60% |
| 152 | Admissions | 660 days | Jan 3 | Jul 13 | Alen Brown,Principal,Gail Snipes | 70% |
| 153 | Decide on order of each piece of the application procedure | 10 days | May 2 | May 13 | Alen Brown,Gail Snipes | 70% |
| 154 | Create each piece to application procedure | 530 days | Jan 3 | Jan 12 | Principal,Gail Snipes | 73% |
| 155 | Proof of income (1040) | 1 day | May 1 | May 1 | Principal,Gail Snipes | 100% |
| 156 | Interview form and format | 12.5 days | May 2 | May 18 | Principal,Gail Snipes | 70% |
| 157 | Define Admissions Testing | 179 days | May 2 | Jan 5 | Gail Snipes | 65% |
| 158 | Decide on Baseline educational achievement. | 180 days | May 8 | Jan 12 | Gail Snipes | 65% |
| 159 | Define Parent/Student Requirements and contracts | 175 days | May 8 | Jan 5 | Thomas James | 78% |
| 160 | Signed "contract" from parent/student on support | 175 days | May 8 | Jan 5 | Alen Brown,Principal,Gail Snipes | 78% |
| 161 | Define Contract | 170 days | May 8 | Dec 29 | Gail Snipes,Alen Brown | 80% |
| 162 | Define Volunteer Work (Parents) | 175 days | May 8 | Jan 5 | Gail Snipes,Alen Brown | 75% |
| 163 | Define monthly fee for children to go (Policy) | 10 days | May 8 | May 19 | Alen Brown,Gail Snipes | 100% |
| 164 | Participation in parent teacher conferences | 2 days | May 8 | May 18 | Alen Brown,Gail Snipes | 100% |
| 165 | Define Low Income Children | 365 days | Jan 3 | May 26 | Alen Brown,Development Dir. | 95% |
| 166 | Definition of "free and reduced" lunch | 15 days | Jan 3 | Jan 21 | Principal,Gail Snipes | 100% |
| 167 | Define St Laurence Policy | 15 days | May 8 | May 26 | Alen Brown | 90% |
| 168 | Entrance Requirements Defined & Reviewed by Legal | 64 days | Mar 1 | May 27 | Alen Brown,Development Dir. | 99% |
| 169 | Preliminary Discussion with Counsel | 5 days | Mar 1 | Mar 7 | Development Dir.,Thomas James | 100% |
| 170 | Discussion with School Legal or Expert | 10 days | May 16 | May 27 | Alen Brown | 100% |
| 171 | Create full Applicatoin Package and place on Web | 168 days | May 17 | Jan 5 | Gail Snipes | 75% |
| 172 | Admit Fifteen Boy's and Fifteen Girl's as 5th grade students | 40 days | May 21 | Jul 13 | Gail Snipes | 0% |
| 173 | Understand facilities plan | 727 days | Aug 27 | Jun 8 | Alen Brown,Development Dir. | 49% |
| 174 | Initial Discussion of Alternatives | 30 days | Aug 27 | Oct 7 | Alen Brown | 100% |
| 175 | Research an Existing Donated Facility | 285 days | Aug 15 | Sep 15 | Alen Brown,Development Dir. | 70% |
| 176 | Research Lease of a Facility | 60 days | Sep 26 | Dec 7 | Alen Brown | 50% |
| 177 | Research Purchasing a Facility | 250 days | Nov 7 | Oct 20 | Alen Brown,Development Dir. | 50% |
| 178 | Research Trailer Classrooms | 235 days | Nov 7 | Sep 29 | Alen Brown | 50% |
| 179 | Research Land Options | 250 days | Nov 7 | Oct 20 | Alen Brown | 50% |
| 180 | Research Diocesan Assistance | 225 days | Jan 2 | Nov 10 | Alen Brown,Development Dir. | 40% |
| 181 | Decide on Initial Facility | 65 days | Mar 12 | Jun 8 | Alen Brown,Gail Snipes | 0% |
| 182 | Define food service plan | 561 days | Apr 4 | May 28 | Alen Brown | 30% |
| 183 | Rersearch Potential Government Monies | 30 days | Apr 4 | May 13 | Joyce Nicholson | 100% |
| 184 | Decisions on Logistics | 120 days | Nov 1 | Apr 16 | Alen Brown | 20% |
| 185 | Commit to Suppliers | 30 days | Apr 17 | May 28 | Alen Brown | 0% |
| 186 | Develop Partnerships | 658 days | Jul 1 | Jan 5 | Alen Brown,Development Dir. | 64% |
| 187 | Define Needs with Partners and Focus Group | 409 days | Mar 1 | Sep 22 | Alen Brown | 80% |
| 188 | Paulding Boys' & Girls' Club | 500 days | Jul 1 | May 30 | Alen Brown,Deborah Betsill | 100% |
| 189 | Tutoring | 500 days | Jul 1 | May 30 | Alen Brown | 100% |
| 190 | Summer Programs | 500 days | Jul 1 | May 30 | Betty Larson | 100% |
| 191 | Episcopal Diocese | 240 days | Feb 14 | Jan 13 | Alen Brown | 52% |
| 192 | Conferences | 10 days | Feb 14 | Feb 25 | Alen Brown | 60% |
| 193 | Property Options | 50 days | Nov 7 | Jan 13 | Alen Brown | 50% |
| 194 | Partner with Cobb Micro Enterprises | 446 days | Nov 14 | Jul 28 | Alen Brown,Development Dir.,Deborah Betsill | 60% |
| 195 | Determine Details | 446 days | Nov 14 | Jul 28 | Alen Brown,Development Dir. | 60% |
| 196 | Research Collaborative for Partners | 410 days | Jan 9 | Aug 4 | Alen Brown | 80% |
| 197 | Reasearch Chattahoochee Tech for GED & Other Classes | 415 days | Jan 2 | Aug 4 | Joyce Nicholson | 60% |
| 198 | Define Other Parners | 209 days | Nov 1 | Aug 18 | Alen Brown | 20% |
| 199 | Make decisions on Initial / Primary Partners | 60 days | Jan 24 | Oct 17 | Alen Brown | 45% |
| 200 | Develop Community Focus Group | 393 days | Jul 1 | Dec 30 | Alen Brown | 56% |
| 201 | Initial Development and Meeting | 20 days | Oct 18 | Nov 12 | Alen Brown | 100% |
| 202 | Decide on members of focus group and elect Chair | 13 days | Jan 12 | Jan 28 | Alen Brown | 100% |
| 203 | Create and pass out survey | 2 days | Feb 1 | Feb 2 | Alen Brown | 100% |
| 204 | Nominate & Elect Chair to Board | 15 days | Apr 4 | Apr 22 | Alen Brown | 100% |
| 205 | Meet to confirm decisions and inform all | 393 days | Jul 1 | Dec 30 | Thomas James | 50% |
| 206 | Memberships | 418 days | Jul 1 | Feb 3 | Alen Brown | 68% |
| 207 | Nativity Network | 63 days | Oct 21 | Jan 14 | Deborah Betsill,Alen Brown | 100% |
| 208 | Nativity Development Conference | 3 days | Oct 21 | Oct 25 | Deborah Betsill,Alen Brown | 100% |
| 209 | Nativity School Operations Conference | 3 days | Jan 12 | Jan 14 | Deborah Betsill,Alen Brown | 100% |
| 210 | Nat'l Assoc. of Episcopal Schools | 25 days | Jul 1 | Aug 4 | Alen Brown | 100% |
| 211 | Georgia Center for Non-Profits | 15 days | Jul 1 | Jul 21 | Alen Brown | 100% |
| 212 | Assoc. Of Fundraising Professionals | 30 days | Dec 26 | Feb 3 | Development Dir. | 20% |
| 213 | Paulding Involvement | 548 days | Jul 1 | Aug 4 | Alen Brown | 100% |
| 214 | Planning for Paulding | 547 days | Jul 2 | Aug 4 | Alen Brown | 100% |
| 215 | Steering Committee Meeting | 547 days | Jul 2 | Aug 4 | Alen Brown | 100% |
| 216 | Steering Committee Meeting 1 | 1 day | Jul 2 | Jul 2 | | 100% |
| 217 | Steering Committee Meeting 2 | 1 day | Aug 6 | Aug 6 | | 100% |
| 218 | Steering Committee Meeting 3 | 1 day | Sep 3 | Sep 3 | | 100% |
| 219 | Steering Committee Meeting 4 | 1 day | Oct 1 | Oct 1 | | 100% |
| 220 | Steering Committee Meeting 5 | 1 day | Nov 5 | Nov 5 | | 100% |
| 221 | Steering Committee Meeting 6 | 1 day | Dec 3 | Dec 3 | | 100% |
| 222 | Steering Committee Meeting 7 | 1 day | Jan 7 | Jan 7 | | 100% |
| 223 | Steering Committee Meeting 8 | 1 day | Feb 4 | Feb 4 | | 100% |
| 224 | Steering Committee Meeting 9 | 1 day | Mar 4 | Mar 4 | | 100% |
| 225 | Steering Committee Meeting 10 | 1 day | Apr 1 | Apr 1 | | 100% |
| 226 | Steering Committee Meeting 11 | 1 day | May 6 | May 6 | | 100% |
| 227 | Steering Committee Meeting 12 | 1 day | Jun 3 | Jun 3 | | 100% |
| 228 | Steering Committee Meeting 13 | 1 day | Jul 1 | Jul 1 | | 100% |
| 229 | Steering Committee Meeting 14 | 1 day | Aug 5 | Aug 5 | | 100% |
| 230 | Steering Committee Meeting 15 | 1 day | Sep 2 | Sep 2 | | 100% |
| 231 | Steering Committee Meeting 16 | 1 day | Oct 7 | Oct 7 | | 100% |
| 232 | Steering Committee Meeting 17 | 1 day | Nov 4 | Nov 4 | | 100% |
| 233 | Steering Committee Meeting 18 | 1 day | Dec 2 | Dec 2 | | 100% |
| 234 | Steering Committee Meeting 19 | 1 day | Jan 6 | Jan 6 | | 100% |
| 235 | Steering Committee Meeting 20 | 1 day | Feb 3 | Feb 3 | | 100% |
| 236 | Steering Committee Meeting 21 | 1 day | Mar 3 | Mar 3 | | 100% |
| 237 | Steering Committee Meeting 22 | 1 day | Apr 7 | Apr 7 | | 100% |
| 238 | Steering Committee Meeting 23 | 1 day | May 5 | May 5 | | 100% |
| 239 | Steering Committee Meeting 24 | 1 day | Jun 2 | Jun 2 | | 100% |
| 240 | Steering Committee Meeting 25 | 1 day | Jul 7 | Jul 7 | | 100% |
| 241 | Steering Committee Meeting 26 | 1 day | Aug 4 | Aug 4 | | 100% |
| 242 | Faith Based Meeting | 527 days | Jul 15 | Jul 20 | Alen Brown | 100% |
| 243 | Faith Based Meeting 1 | 1 day | Jul 15 | Jul 15 | | 100% |
| 244 | Faith Based Meeting 2 | 1 day | Aug 19 | Aug 19 | | 100% |
| 245 | Faith Based Meeting 3 | 1 day | Sep 16 | Sep 16 | | 100% |
| 246 | Faith Based Meeting 4 | 1 day | Oct 21 | Oct 21 | | 100% |
| 247 | Faith Based Meeting 5 | 1 day | Nov 18 | Nov 18 | | 100% |
| 248 | Faith Based Meeting 6 | 1 day | Dec 16 | Dec 16 | | 100% |
| 249 | Faith Based Meeting 7 | 1 day | Jan 20 | Jan 20 | | 100% |
| 250 | Faith Based Meeting 8 | 1 day | Feb 17 | Feb 17 | | 100% |
| 251 | Faith Based Meeting 9 | 1 day | Mar 17 | Mar 17 | | 100% |
| 252 | Faith Based Meeting 10 | 1 day | Apr 21 | Apr 21 | | 100% |
| 253 | Faith Based Meeting 11 | 1 day | May 19 | May 19 | | 100% |
| 254 | Faith Based Meeting 12 | 1 day | Jun 16 | Jun 16 | | 100% |
| 255 | Faith Based Meeting 13 | 1 day | Jul 21 | Jul 21 | | 100% |
| 256 | Faith Based Meeting 14 | 1 day | Aug 18 | Aug 18 | | 100% |
| 257 | Faith Based Meeting 15 | 1 day | Sep 15 | Sep 15 | | 100% |
| 258 | Faith Based Meeting 16 | 1 day | Oct 20 | Oct 20 | | 100% |
| 259 | Faith Based Meeting 17 | 1 day | Nov 17 | Nov 17 | | 100% |
| 260 | Faith Based Meeting 18 | 1 day | Dec 15 | Dec 15 | | 100% |
| 261 | Faith Based Meeting 19 | 1 day | Jan 19 | Jan 19 | | 100% |
| 262 | Faith Based Meeting 20 | 1 day | Feb 16 | Feb 16 | | 100% |
| 263 | Faith Based Meeting 21 | 1 day | Mar 16 | Mar 16 | | 100% |
| 264 | Faith Based Meeting 22 | 1 day | Apr 20 | Apr 20 | | 100% |
| 265 | Faith Based Meeting 23 | 1 day | May 18 | May 18 | | 100% |
| 266 | Faith Based Meeting 24 | 1 day | Jun 15 | Jun 15 | | 100% |
| 267 | Faith Based Meeting 25 | 1 day | Jul 20 | Jul 20 | | 100% |
| 268 | Education Meeting | 542 days | Jul 7 | Aug 2 | Alen Brown | 100% |
| 269 | Education Meeting 1 | 1 day | Jul 7 | Jul 7 | | 100% |
| 270 | Education Meeting 2 | 1 day | Aug 4 | Aug 4 | | 100% |
| 271 | Education Meeting 3 | 1 day | Sep 1 | Sep 1 | | 100% |
| 272 | Education Meeting 4 | 1 day | Oct 6 | Oct 6 | | 100% |
| 273 | Education Meeting 5 | 1 day | Nov 3 | Nov 3 | | 100% |
| 274 | Education Meeting 6 | 1 day | Dec 1 | Dec 1 | | 100% |
| 275 | Education Meeting 7 | 1 day | Jan 5 | Jan 5 | | 100% |
| 276 | Education Meeting 8 | 1 day | Feb 2 | Feb 2 | | 100% |
| 277 | Education Meeting 9 | 1 day | Mar 2 | Mar 2 | | 100% |
| 278 | Education Meeting 10 | 1 day | Apr 6 | Apr 6 | | 100% |
| 279 | Education Meeting 11 | 1 day | May 4 | May 4 | | 100% |
| 280 | Education Meeting 12 | 1 day | Jun 1 | Jun 1 | | 100% |
| 281 | Education Meeting 13 | 1 day | Jul 6 | Jul 6 | | 100% |
| 282 | Education Meeting 14 | 1 day | Aug 3 | Aug 3 | | 100% |
| 283 | Education Meeting 15 | 1 day | Sep 7 | Sep 7 | | 100% |
| 284 | Education Meeting 16 | 1 day | Oct 5 | Oct 5 | | 100% |
| 285 | Education Meeting 17 | 1 day | Nov 2 | Nov 2 | | 100% |
| 286 | Education Meeting 18 | 1 day | Dec 7 | Dec 7 | | 100% |
| 287 | Education Meeting 19 | 1 day | Jan 4 | Jan 4 | | 100% |
| 288 | Education Meeting 20 | 1 day | Feb 1 | Feb 1 | | 100% |
| 289 | Education Meeting 21 | 1 day | Mar 1 | Mar 1 | | 100% |
| 290 | Education Meeting 22 | 1 day | Apr 5 | Apr 5 | | 100% |
| 291 | Education Meeting 23 | 1 day | May 3 | May 3 | | 100% |
| 292 | Education Meeting 24 | 1 day | Jun 7 | Jun 7 | | 100% |
| 293 | Education Meeting 25 | 1 day | Jul 5 | Jul 5 | | 100% |
| 294 | Education Meeting 26 | 1 day | Aug 2 | Aug 2 | | 100% |
| 295 | Paulding Collaborative | 527 days | Jul 16 | Jul 21 | Development Dir. | 100% |
| 296 | Paulding Collaborative 1 | 1 day | Jul 16 | Jul 16 | Development Dir. | 100% |
| 297 | Paulding Collaborative 2 | 1 day | Aug 20 | Aug 20 | Development Dir. | 100% |
| 298 | Paulding Collaborative 3 | 1 day | Sep 17 | Sep 17 | Development Dir. | 100% |
| 299 | Paulding Collaborative 4 | 1 day | Oct 15 | Oct 15 | Development Dir. | 100% |
| 300 | Paulding Collaborative 5 | 1 day | Nov 19 | Nov 19 | Development Dir. | 100% |
| 301 | Paulding Collaborative 6 | 1 day | Dec 17 | Dec 17 | Development Dir. | 100% |
| 302 | Paulding Collaborative 7 | 1 day | Jan 21 | Jan 21 | Development Dir. | 100% |
| 303 | Paulding Collaborative 8 | 1 day | Feb 18 | Feb 18 | Development Dir. | 100% |
| 304 | Paulding Collaborative 9 | 1 day | Mar 18 | Mar 18 | Development Dir. | 100% |
| 305 | Paulding Collaborative 10 | 1 day | Apr 15 | Apr 15 | Development Dir. | 100% |
| 306 | Paulding Collaborative 11 | 1 day | May 20 | May 20 | Development Dir. | 100% |
| 307 | Paulding Collaborative 12 | 1 day | Jun 17 | Jun 17 | Development Dir. | 100% |
| 308 | Paulding Collaborative 13 | 1 day | Jul 15 | Jul 15 | Development Dir. | 100% |
| 309 | Paulding Collaborative 14 | 1 day | Aug 19 | Aug 19 | Development Dir. | 100% |
| 310 | Paulding Collaborative 15 | 1 day | Sep 16 | Sep 16 | Development Dir. | 100% |
| 311 | Paulding Collaborative 16 | 1 day | Oct 21 | Oct 21 | Development Dir. | 100% |
| 312 | Paulding Collaborative 17 | 1 day | Nov 18 | Nov 18 | Development Dir. | 100% |
| 313 | Paulding Collaborative 18 | 1 day | Dec 16 | Dec 16 | Development Dir. | 100% |
| 314 | Paulding Collaborative 19 | 1 day | Jan 20 | Jan 20 | Development Dir. | 100% |
| 315 | Paulding Collaborative 20 | 1 day | Feb 17 | Feb 17 | Development Dir. | 100% |
| 316 | Paulding Collaborative 21 | 1 day | Mar 17 | Mar 17 | Development Dir. | 100% |
| 317 | Paulding Collaborative 22 | 1 day | Apr 21 | Apr 21 | Development Dir. | 100% |
| 318 | Paulding Collaborative 23 | 1 day | May 19 | May 19 | Development Dir. | 100% |
| 319 | Paulding Collaborative 24 | 1 day | Jun 16 | Jun 16 | Development Dir. | 100% |
| 320 | Paulding Collaborative 25 | 1 day | Jul 21 | Jul 21 | Development Dir. | 100% |
| 321 | Paulding Chamber of Commerce | 547 days | Jul 1 | Aug 3 | Alen Brown | 100% |
| 322 | Paulding Chamber of Commerce 1 | 1 day | Jul 1 | Jul 1 | | 100% |
| 323 | Paulding Chamber of Commerce 2 | 1 day | Aug 5 | Aug 5 | | 100% |
| 324 | Paulding Chamber of Commerce 3 | 1 day | Sep 2 | Sep 2 | | 100% |
| 325 | Paulding Chamber of Commerce 4 | 1 day | Oct 7 | Oct 7 | | 100% |
| 326 | Paulding Chamber of Commerce 5 | 1 day | Nov 4 | Nov 4 | | 100% |
| 327 | Paulding Chamber of Commerce 6 | 1 day | Dec 2 | Dec 2 | | 100% |
| 328 | Paulding Chamber of Commerce 7 | 1 day | Jan 6 | Jan 6 | | 100% |
| 329 | Paulding Chamber of Commerce 8 | 1 day | Feb 3 | Feb 3 | | 100% |
| 330 | Paulding Chamber of Commerce 9 | 1 day | Mar 3 | Mar 3 | | 100% |
| 331 | Paulding Chamber of Commerce 10 | 1 day | Apr 7 | Apr 7 | | 100% |
| 332 | Paulding Chamber of Commerce 11 | 1 day | May 5 | May 5 | | 100% |
| 333 | Paulding Chamber of Commerce 12 | 1 day | Jun 2 | Jun 2 | | 100% |
| 334 | Paulding Chamber of Commerce 13 | 1 day | Jul 7 | Jul 7 | | 100% |
| 335 | Paulding Chamber of Commerce 14 | 1 day | Aug 4 | Aug 4 | | 100% |
| 336 | Paulding Chamber of Commerce 15 | 1 day | Sep 1 | Sep 1 | | 100% |
| 337 | Paulding Chamber of Commerce 16 | 1 day | Oct 6 | Oct 6 | | 100% |
| 338 | Paulding Chamber of Commerce 17 | 1 day | Nov 3 | Nov 3 | | 100% |
| 339 | Paulding Chamber of Commerce 18 | 1 day | Dec 1 | Dec 1 | | 100% |
| 340 | Paulding Chamber of Commerce 19 | 1 day | Jan 5 | Jan 5 | | 100% |
| 341 | Paulding Chamber of Commerce 20 | 1 day | Feb 2 | Feb 2 | | 100% |
| 342 | Paulding Chamber of Commerce 21 | 1 day | Mar 2 | Mar 2 | | 100% |
| 343 | Paulding Chamber of Commerce 22 | 1 day | Apr 6 | Apr 6 | | 100% |
| 344 | Paulding Chamber of Commerce 23 | 1 day | May 4 | May 4 | | 100% |
| 345 | Paulding Chamber of Commerce 24 | 1 day | Jun 1 | Jun 1 | | 100% |
| 346 | Paulding Chamber of Commerce 25 | 1 day | Jul 6 | Jul 6 | | 100% |
| 347 | Paulding Chamber of Commerce 26 | 1 day | Aug 3 | Aug 3 | | 100% |
| 348 | Atlanta Universities | 500 days | Feb 7 | Jan 5 | Alen Brown | 34% |
| 349 | For Interns and Volunteers | 500 days | Feb 7 | Jan 5 | Alen Brown | 34% |
| 350 | Kennesaw State | 385 days | Jul 18 | Jan 5 | Alen Brown | 40% |
| 351 | Spelman | 500 days | Feb 7 | Jan 5 | Alen Brown | 40% |
| 352 | Georgia State | 380 days | Jul 25 | Jan 5 | Alen Brown | 20% |
| 353 | For Scholarships to High School graduates | 387 days | Feb 7 | Aug 1 | Alen Brown | 20% |
| 354 | Kennesaw State | 1 day | Jul 18 | Jul 18 | Alen Brown | 20% |
| 355 | Spelman | 1 day | Feb 7 | Feb 7 | Alen Brown | 20% |
| 356 | Georgia State | 1 day | Aug 1 | Aug 1 | Alen Brown | 20% |
| 357 | Volunteer donations | 804 days | Jul 1 | Jul 30 | Development Dir. | 51% |
| 358 | Define Volunteer Program (non Family Members) | 783 days | Jul 1 | Jun 29 | Development Dir.,Alen Brown | 52% |
| 359 | Define Needs | 425 days | Aug 8 | Mar 23 | Principal,Alen Brown,Gail Snipes | 53% |
| 360 | Determine specific needed in kind professional services | 425 days | Aug 8 | Mar 23 | Alen Brown,Development Dir. | 53% |
| 361 | Legal | 425 days | Aug 8 | Mar 23 | Alen Brown | 65% |
| 362 | Accounting | 420 days | Aug 8 | Mar 16 | Alen Brown | 65% |
| 363 | Food | 420 days | Aug 8 | Mar 16 | Alen Brown | 25% |
| 364 | Tutoring/Mentoring | 420 days | Aug 8 | Mar 16 | Principal,Gail Snipes | 45% |
| 365 | After School Program | 420 days | Aug 8 | Mar 16 | Principal,Gail Snipes | 65% |
| 366 | Define roles/responsibilities of Interns | 708 days | Jul 1 | Mar 16 | Alen Brown,Development Dir. | 50% |
| 367 | Research Interns (Americorp, etc) | 22 days | May 2 | May 31 | Joyce Nicholson | 100% |
| 368 | Apply to Americorp | 30 days | Aug 22 | May 1 | Development Dir. | 10% |
| 369 | Apply to Jesuit Volunteers | 30 days | Oct 3 | Jun 7 | Development Dir. | 10% |
| 370 | Solicit Paulding Community Members | 22 days | Nov 14 | Jun 29 | Development Dir. | 27% |
| 371 | Acquire Volunteer Coordinator on Staff | 21 days | Jul 2 | Jul 30 | Alen Brown | 0% |
| 372 | Business Operations | 788 days | Jul 1 | Jul 6 | Alen Brown | 42% |
| 373 | Human Resources | 783 days | Jul 1 | Jun 29 | Alen Brown | 55% |
| 374 | Develop Job Descriptions for Exec Dir, Board, & Development Dir | 20 days | Feb 14 | Mar 11 | Alen Brown | 100% |
| 375 | Hire Executive Director | 5 days | Dec 21 | Dec 27 | Board Members | 100% |
| 376 | Rersearch Interviewing Procedures and methods | 2 days | Feb 7 | Feb 8 | Alen Brown | 100% |
| 377 | Hire part time bookeeper | 10 days | Jul 1 | Jul 14 | Alen Brown | 100% |
| 378 | Train on technology and process | 10 days | Jul 1 | Jul 14 | Alen Brown | 100% |
| 379 | Develop Employee Manual and forms | 339.5 days | Oct 25 | Feb 9 | Alen Brown | 43% |
| 380 | Purchase template written by Lawyer | 2 days | May 16 | May 17 | Alen Brown | 100% |
| 381 | Combine with Academy Prep & Blueprint versions | 3 days | May 16 | May 18 | Alen Brown | 100% |
| 382 | Develop Safety Manual based on Academy Prep manual | 10 days | Oct 25 | Feb 9 | Alen Brown | 15% |
| 383 | Initial Payroll company Setup-ADP | 5 days | Jul 1 | Jul 7 | Alen Brown | 100% |
| 384 | Change payroll company to Paychex after evaluation of options | 10 days | Feb 7 | Feb 18 | Alen Brown | 100% |
| 385 | Hire Development Director | 180 days | May 2 | Jan 6 | Alen Brown | 82% |
| 386 | Post Position | 15 days | May 2 | May 20 | Alen Brown | 100% |
| 387 | Conduct Interviews | 20 days | May 23 | Jun 17 | Alen Brown | 100% |
| 388 | Have Board Interview final candidates | 10 days | Jun 20 | Jul 1 | Board Members | 100% |
| 389 | Train DD on technology and process | 10 days | Jun 20 | Jul 1 | Alen Brown | 100% |
| 390 | Hire Development Director | 10 days | Dec 26 | Jan 6 | Alen Brown | 0% |
| 391 | Train DD on technology and process | 10 days | Dec 26 | Jan 6 | Alen Brown | 0% |
| 392 | Hire Principal | 50 days | Oct 24 | Dec 30 | Alen Brown | 0% |
| 393 | Post Position | 5 days | Oct 24 | Oct 28 | Alen Brown | 0% |
| 394 | Conduct Interviews | 20 days | Oct 31 | Nov 25 | Alen Brown | 0% |
| 395 | Have Board Interview final candidates | 25 days | Nov 28 | Dec 30 | Board Members | 0% |
| 396 | Mix of paid and volunteer staff resources | 434 days | Jul 5 | Mar 2 | Alen Brown | 58% |
| 397 | Define roles & responsibilities | 434 days | Jul 5 | Mar 2 | Alen Brown,Gail Snipes | 58% |
| 398 | Master Organization Chart | 20 days | Jul 5 | Aug 1 | Alen Brown | 100% |
| 399 | Teachers | 320 days | Oct 3 | Dec 22 | Gail Snipes | 59% |
| 400 | Admin | 335 days | Oct 3 | Jan 12 | Alen Brown | 60% |
| 401 | Contracted Services (Transportation) | 305 days | Jan 2 | Mar 2 | Alen Brown | 51% |
| 402 | Define Staff compensation/benefits. | 629 days | Feb 1 | Jun 29 | Alen Brown | 39% |
| 403 | Research Options | 30 days | Feb 1 | Mar 14 | Joyce Nicholson | 100% |
| 404 | Define compensation/benefits | 40 days | Jan 5 | Mar 1 | Alen Brown | 100% |
| 405 | Hire First School Year Staff | 152.55 days | Apr 3 | Jun 29 | Alen Brown,Gail Snipes | 12% |
| 406 | Accounting | 788 days | Jul 1 | Jul 6 | Faith Turner | 31% |
| 407 | Understanding accounting for non-profit organizations | 60 days | Feb 1 | Apr 25 | Beth Grzech,Alen Brown | 100% |
| 408 | Build Website and setup for online donations | 40 days | Jul 12 | Sep 3 | Alen Brown | 100% |
| 409 | Choose Financial Institutions and Setup | 10 days | Jul 1 | Jul 14 | Alen Brown,Beth Grzech | 100% |
| 410 | Operational Expenses | 633 days | Feb 2 | Jul 6 | Alen Brown,Development Dir. | 24% |
| 411 | Start Up | 628 days | Feb 2 | Jun 29 | Alen Brown,Development Dir. | 30% |
| 412 | 1st Year | 500 days | Aug 8 | Jul 6 | Alen Brown,Development Dir. | 17% |
| 413 | Decide on when Required Funds are needed to Open | 120 days | Aug 8 | Feb 26 | Alen Brown | 28% |
| 414 | Make adjustments as necessary to look at options | 395 days | Jan 2 | Jul 6 | Alen Brown | 14% |
| 415 | Risk and Legal evaluations | 627 days | Aug 27 | Jan 19 | TBD | 31% |
| 416 | Understanding legal Implications | 22 days | Mar 1 | Mar 30 | Joyce Nicholson | 80% |
| 417 | Understand and obtain insurance requirements | 80 days | Mar 6 | Jun 23 | Alen Brown | 95% |
| 418 | Insurance Reqs outside of Liability | 20 days | Mar 6 | Mar 31 | Joyce Nicholson | 80% |
| 419 | Develop policies, rules and put in place to obtain insurance | 60 days | Apr 3 | Jun 23 | Alen Brown | 100% |
| 420 | Liability insurance for volunteers | 627 days | Aug 27 | Jan 19 | Alen Brown | 21% |
| 421 | D & O Insurance | 30 days | Jul 1 | Aug 23 | Alen Brown | 100% |
| 422 | Tutoring | 0 days | Aug 27 | Aug 27 | Alen Brown | 100% |
| 423 | Other Volunteers (non Tutor) | 166 days | Jun 2 | Jan 19 | Joyce Nicholson | 7% |
| 424 | Liability Insurance for Staff | 165 days | Jun 5 | Jan 19 | Joyce Nicholson | 5% |
| 425 | Idemnification Insurance | 20 days | Jun 5 | Jun 30 | Joyce Nicholson | 40% |
| 426 | Technology | 544 days | Jul 1 | Jul 31 | Alen Brown | 61% |
| 427 | Obtain Initial computer/software for Business and presentations | 15 days | Jul 1 | Jul 21 | Alen Brown | 100% |
| 428 | Setup | 15 days | Jul 1 | Jul 21 | Alen Brown | 100% |
| 429 | Obtain LCD Projector | 2 days | Jul 1 | Jul 2 | Alen Brown | 100% |
| 430 | Obtain Quality Network Printer for literature production | 3 days | Jan 3 | Jan 5 | Alen Brown | 100% |
| 431 | Setup | 3 days | Jan 3 | Jan 5 | Alen Brown | 100% |
| 432 | Setup Website for On-line donations | 10 days | Dec 1 | Dec 14 | Alen Brown | 100% |
| 433 | Obtain Second Laptop for Development Director | 5 days | Mar 7 | Mar 11 | Alen Brown | 100% |
| 434 | Setup | 5 days | Mar 7 | Mar 11 | Alen Brown | 100% |
| 435 | Obtain Network Harddrive for Database Manager syncronization | 2 days | May 2 | May 3 | Alen Brown | 100% |
| 436 | Setup | 2 days | May 2 | May 3 | Alen Brown | 100% |
| 437 | Obtain Desktop Computer | 7 days | Jun 6 | Jun 14 | Alen Brown | 100% |
| 438 | Setup | 7 days | Jun 6 | Jun 14 | Alen Brown | 100% |
| 439 | Develop Database Manager for group mailings using templates | 25 days | Jun 20 | Jul 22 | Alen Brown | 100% |
| 440 | Update Project File | 522 days | Aug 2 | Jul 31 | Alen Brown | 0% |
| 441 | Update Project File 1 | 1 day | Aug 2 | Aug 2 | | 0% |
| 442 | Update Project File 2 | 1 day | Aug 31 | Aug 31 | | 0% |
| 443 | Update Project File 3 | 1 day | Sep 30 | Sep 30 | | 0% |
| 444 | Update Project File 4 | 1 day | Nov 1 | Nov 1 | | 0% |
| 445 | Update Project File 5 | 1 day | Nov 30 | Nov 30 | | 0% |
| 446 | Update Project File 6 | 1 day | Dec 31 | Dec 31 | | 0% |
| 447 | Update Project File 7 | 1 day | Jan 31 | Jan 31 | | 0% |
| 448 | Update Project File 8 | 1 day | Feb 28 | Feb 28 | | 0% |
| 449 | Update Project File 9 | 1 day | Mar 31 | Mar 31 | | 0% |
| 450 | Update Project File 10 | 1 day | May 2 | May 2 | | 0% |
| 451 | Update Project File 11 | 1 day | May 31 | May 31 | | 0% |
| 452 | Update Project File 12 | 1 day | Jun 30 | Jun 30 | | 0% |
| 453 | Update Project File 13 | 1 day | Aug 1 | Aug 1 | | 0% |
| 454 | Update Project File 14 | 1 day | Aug 31 | Aug 31 | | 0% |
| 455 | Update Project File 15 | 1 day | Sep 30 | Sep 30 | | 0% |
| 456 | Update Project File 16 | 1 day | Oct 31 | Oct 31 | | 0% |
| 457 | Update Project File 17 | 1 day | Nov 30 | Nov 30 | | 0% |
| 458 | Update Project File 18 | 1 day | Jan 2 | Jan 2 | | 0% |
| 459 | Update Project File 19 | 1 day | Jan 31 | Jan 31 | | 0% |
| 460 | Update Project File 20 | 1 day | Feb 28 | Feb 28 | | 0% |
| 461 | Update Project File 21 | 1 day | Mar 31 | Mar 31 | | 0% |
| 462 | Update Project File 22 | 1 day | May 1 | May 1 | | 0% |
| 463 | Update Project File 23 | 1 day | May 31 | May 31 | | 0% |
| 464 | Update Project File 24 | 1 day | Jun 30 | Jun 30 | | 0% |
| 465 | Update Project File 25 | 1 day | Jul 31 | Jul 31 | | 0% |
| 466 | Update Project File 1 | 1 day | Aug 31 | Aug 31 | | 0% |
| 467 | Update Project File 2 | 1 day | Sep 30 | Sep 30 | | 0% |
| 468 | Update Project File 3 | 1 day | Oct 31 | Oct 31 | | 0% |
| 469 | Update Project File 4 | 1 day | Nov 30 | Nov 30 | | 0% |
| 470 | Update Project File 5 | 1 day | Jan 31 | Jan 31 | | 0% |
| 471 | Update Project File 6 | 1 day | Feb 28 | Feb 28 | | 0% |
| 472 | Update Project File 7 | 1 day | Mar 31 | Mar 31 | | 0% |
| 473 | Update Project File 8 | 1 day | May 31 | May 31 | | 0% |
| 474 | Update Project File 9 | 1 day | Jun 30 | Jun 30 | | 0% |
| 475 | Update Project File 10 | 1 day | Jul 31 | Jul 31 | | 0% |
| 476 | Update Website | 239 days | Aug 31 | Jul 31 | | 0% |
| 477 | Update Website 1 | 1 day | Aug 31 | Aug 31 | | 0% |
| 478 | Update Website 2 | 1 day | Sep 30 | Sep 30 | | 0% |
| 479 | Update Website 3 | 1 day | Oct 31 | Oct 31 | | 0% |
| 480 | Update Website 4 | 1 day | Nov 30 | Nov 30 | | 0% |
| 481 | Update Website 5 | 1 day | Jan 31 | Jan 31 | | 0% |
| 482 | Update Website 6 | 1 day | Feb 28 | Feb 28 | | 0% |
| 483 | Update Website 7 | 1 day | Mar 31 | Mar 31 | | 0% |
| 484 | Update Website 8 | 1 day | May 31 | May 31 | | 0% |
| 485 | Update Website 9 | 1 day | Jun 30 | Jun 30 | | 0% |
| 486 | Update Website 10 | 1 day | Jul 31 | Jul 31 | | 0% |
| 487 | Graduate assistance program | 637 days | Aug 27 | Feb 2 | Alen Brown,Development Dir. | 56% |
| 488 | Building relationships with current metro-Atlanta schools | 552 days | Aug 27 | Oct 6 | Alen Brown,Development Dir. | 62% |
| 489 | Begin relationships with Atlanta schools | 504 days | Aug 27 | Aug 1 | Alen Brown,Development Dir. | 40% |
| 490 | Understand the targeted high school acceptance criteria | 385 days | Apr 17 | Oct 6 | Alen Brown,Development Dir. | 90% |
| 491 | Address socio-economic & cultural challenges for placement | 1 day | Apr 17 | Aug 1 | Development Dir.,Alen Brown | 10% |
| 492 | Begin Discussions with Universities | 280 days | Jan 8 | Feb 2 | Development Dir.,Alen Brown | 40% |
| 493 | Sewanee | 280 days | Jan 8 | Feb 2 | Alen Brown | 40% |
| 494 | Open School | 0 days | Jul 15 | Jul 15 | Alen Brown,Development Dir.,Gail Snipes | 0% |